EGI Logo

Teed Substations for
Germany's Energy Transition

Faster · Cheaper · Standardised

EGI Strategic Pitch Germany · 2026 Full EPC
EGI The Problem

Germany's Grid Connection Bottleneck

Renewable energy projects are ready — but grid connection backlogs are stalling the Energiewende

0
PV to connect by 2030
50Hertz target
€9B
Annual economic drag
EU connection queue delays
2030
Stalled queue until
Some solar farms waiting

50Hertz must connect 13 GW PV, 11 GW batteries, 2 GW wind by 2030. Connection speed — not permits — is the critical path. Small teed substations are the fastest unlock.

EGI The Solution

Teed Substation Deployment — The EGI Way

🔌

T-Connection on Existing Lines

Tap into existing 50Hertz transmission lines. No new line corridors — faster permitting, lower civil cost.

🧩

Legonet™ Standardised Design

Adapt Elia's proven Legonet modular standards to 50Hertz specifications — off-the-shelf components, repeatable layouts.

⚙️

Full EPCM Scope

Primary systems, Secondary systems, FACTS, Cables, Civil Works. Single accountability. One contract. Zero gaps.

🏗️

€15M Budget Per Station

Compact budget driven by standardisation. 2 stations in parallel. Construction start 2025. Third-party clients welcome.

EGI Why EGI

Unique Positioning in the German Market

300+
Projects in 20+ countries
50Hertz
Sister TSO · Shared DNA
30–380kV
Full voltage range
✓ Insider knowledge of 50Hertz standards

EGI is a subsidiary of Elia Group, which owns 50Hertz. EGI understands technical requirements, workflows, and approval processes from the inside.

✓ Proven experience on similar projects

Gransee, Heinersdorf, Altdöbern, Teufelsbruch substations already delivered. Tapped substation and T-line expertise is battle-tested.

✓ Existing framework agreements with 50Hertz

Active commercial relationship reduces procurement time and de-risks new projects from day one.

EGI Standardisation

Legonet Standard → 50Hertz Adaptation

Applying Elia Belgium's modular substation framework to the specific requirements of the 50Hertz network

Legonet Principles
  • Pre-engineered, repeatable substation blocks
  • Off-the-shelf standardised equipment selections
  • Factory-tested secondary systems panels
  • Common civil and structural layouts
  • Scalable: single or double transformer bays
50Hertz Adaptation Layer
  • Aligned with 50Hertz grid codes and technical specs
  • Teed / T-connection configurations (6 types)
  • German regulatory permitting pathways pre-mapped
  • Protection and SCADA integration with 50Hertz systems
  • Optimised for RES (PV, Wind, Battery) connection

Key benefit: Standardisation cuts design time by ~40%, reduces procurement lead times, enables parallel delivery of 2 stations — at a target budget of €15M per substation.

EGI Technical Reference

Teed Substation Topology Variants

Six standard configurations — from simple single-transformer tees to double-tee T-lines with multiple transformers

TYPE 1 — Single Tee · 1 Transformer

Basic T-connection on existing line. Simplest, fastest deployment. Ideal for single RES generator.

TYPE 2 — Double Tee · 2 Transformers

Twin tap on same line segment. Efficient for co-located wind + solar or battery + PV.

TYPE 3 — Line-End Tee · 1 Transformer

Termination at line end with tap. No loop-through required. Lower switchgear count.

TYPE 4 — Line-End Double Tee · 2 Tfmrs

Dual transformer at line terminus. Maximum capacity from a single corridor access point.

TYPE 5 — T-Triangle · 1 Transformer

Delta configuration for redundancy. Preferred for critical loads or anchor generators.

TYPE 6 — T-Triangle · 2 Transformers

Full N-1 secure triangle tee. Highest reliability. Used for large battery or multi-RES clusters.

EGI Delivery Model

Full EPC — Total EGI Responsibility

EGI Full Scope
1
Primary Systems
HV switchgear, transformers, busbars
2
Secondary Systems
Protection, control, SCADA, telecom
3
FACTS
Reactive power compensation, SVCs
4
Cables
Underground HV cables up to 400kV
5
Civil Works
Foundations, roads, fencing, site prep
Scale-Up Strategy
🎯 Dedicated Specialised Team

A specialised T-substation cell within EGI — engineers trained on 50Hertz standards, permanently staffed to own the full delivery pipeline.

🤝 Local Firm Partnership / Acquisition

EGI may team with or acquire a German engineering firm to rapidly scale capacity, access local labour, and accelerate permitting.

📋 Third-Party Expansion

Framework extended to DSOs, industrial consumers, battery developers — under the same standardised model.

EGI Programme

Rollout Roadmap

Phase 0 — Foundation
2025 Q1–Q2

Establish dedicated team · Adapt Legonet to 50Hertz specs · Formalise framework agreement · Site selection

Phase 1 — First Construction
2025 Q3–Q4

Construction start Station 1 · Procurement via existing framework · Standardised Legonet drawings · 18-month target commissioning

Phase 2 — Parallel Delivery
2026

Station 2 in parallel · Local firm teaming / acquisition finalised · Third-party pipeline activated

Phase 3 — Scale
2027+

Industrialised delivery model · 4+ stations/year · Extended to other 50Hertz connection types · Full German market presence

EGI Value Proposition

What EGI Brings to 50Hertz & Clients

Three distinct advantages no other contractor can replicate

Speed

Standardised designs = no re-engineering. Existing framework cuts lead times. 2 stations in parallel.

💶

Cost Reduction

Legonet standardisation targets €15M/station. Engineering reuse reduces capex ~20–30% per successive project.

🏅

Quality Assurance

Full EPC accountability. EGI carries 50Hertz DNA — delivering to the operator's own standards.

For 50Hertz: Faster RES integration, lower connection costs, trusted delivery partner with insider knowledge.

For RES developers: Predictable timelines, bankable technical solution, single EPC contact — improving project IRR.

EGI Logo
Next Steps

EGI — The Right Partner
for Germany's Grid Sprint

EGI proposes to establish a dedicated Teed Substation delivery unit in Germany, leveraging Legonet standards and 50Hertz insider expertise to connect renewable generators and loads faster and cheaper than any other contractor.

Step 1
Approve dedicated team formation & Legonet adaptation programme
Step 2
Identify first 2 pilot sites with 50Hertz pipeline
Step 3
Evaluate local German engineering firm partnership / acquisition

Elia Grid International · eliagrid-int.com